término |
definición |
empezar lección
|
|
The actual amount of monies the project has spent to date.
|
|
|
empezar lección
|
|
An approach that relies on historical information to predict the cost of the current project. It is also known as top- down estimating and is the least reliable of all the cost-estimating approaches.
|
|
|
empezar lección
|
|
This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates. The range of variance for the estimate can be from –10 percent to +25 percent.
|
|
|
empezar lección
|
|
A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.
|
|
|
empezar lección
|
|
A contingency allowance to account for overruns in costs. Contingency allowances are used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events.
|
|
|
empezar lección
|
|
Costs are parallel to each WBS work package. The costs of each work package are aggregated to their corresponding control accounts. Each control account then is aggregated to the sum of the project costs.
|
|
|
empezar lección
|
|
A time-lapse exposure of when the project monies are to be spent in relation to cumulative values of the work completed in the project.
|
|
|
empezar lección
|
|
The cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS. Cost budgeting applies the cost estimates over time.
|
|
|
Cost change control system empezar lección
|
|
A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources, and the associated impact on the overall project cost.
|
|
|
empezar lección
|
|
The cost management plan dictates how cost variances will be managed.
|
|
|
empezar lección
|
|
The monies spent to attain the expected level of quality within a project. Examples include training, testing, and safety precautions.
|
|
|
Cost performance index (CPI) empezar lección
|
|
"Measures the project based on its financial performance. The formula is CPI
|
|
|
empezar lección
|
|
|
|
|
empezar lección
|
|
The difference of the earned value amount and the cumulative actual costs of the project. The formula is CV = EV – AC.
|
|
|
empezar lección
|
|
"This estimate type is one of the most accurate. It’s used late in the planning processes and is associated with bottom- up estimating. You need the WBS in order to create the definitive estimate.
|
|
|
The range of variance for the estimate can be from –5 percent to +10 percent." empezar lección
|
|
The range of variance for the estimate can be from –5 percent to +10 percent. "
|
|
|
empezar lección
|
|
"Costs are attributed directly to the project work and cannot be shared among projects (for example, airfare, hotels,
|
|
|
long-distance phone charges, and so on)." empezar lección
|
|
long-distance phone charges, and so on). "
|
|
|
empezar lección
|
|
Earned value is the physical work completed to date and the authorized budget for that work. It is the percentage of the BAC that represents the actual work completed in the project.
|
|
|
Estimate at completion (EAC) empezar lección
|
|
These forecasting formulas predict the likely completed costs of the project based on current scenarios within the project.
|
|
|
Estimate to complete (ETC) empezar lección
|
|
"An earned value management formula that predicts how much funding the project will require to be completed.
|
|
|
Three variations of this formula are based on conditions the project may be experiencing." empezar lección
|
|
Three variations of this formula are based on conditions the project may be experiencing. "
|
|
|
empezar lección
|
|
Costs that remain constant throughout the life of the project (the cost of a piece of rented equipment for the project, the cost of a consultant brought on to the project, and so on).
|
|
|
Funding limit reconciliation empezar lección
|
|
An organization’s approach to managing cash flow against the project deliverables based on a schedule, milestone accomplishment, or data constraints.
|
|
|
empezar lección
|
|
Costs that are representative of more than one project (for example, utilities for the performing organization, access to a training room, project management software license, and so on).
|
|
|
empezar lección
|
|
An event that will likely happen within the project, but when it will happen and to what degree is unknown. These events, such as delays, are usually risk-related.
|
|
|
empezar lección
|
|
An approach that assumes the cost per unit decreases the more units workers complete, because workers learn as they complete the required work.
|
|
|
empezar lección
|
|
A market condition where the market is so tight that the actions of one vendor affect the actions of all the others.
|
|
|
empezar lección
|
|
The total cost of the opportunity that is refused to realize an opposing opportunity.
|
|
|
empezar lección
|
|
An approach using a parametric model to extrapolate what costs will be needed for a project (for example, cost per hour and cost per unit). It can include variables and points based on conditions.
|
|
|
empezar lección
|
|
Planned value is the work scheduled and the budget authorized to accomplish that work. It is the percentage of the BAC that reflects where the project should be at this point in time.
|
|
|
empezar lección
|
|
The final variance, which is discovered only at the project’s completion. The formula is VAR = BAC – AC.
|
|
|
empezar lección
|
|
Cost reserves are for unknown unknowns within a project. The management reserve is not part of the project cost baseline, but is included as part of the project budget.
|
|
|
empezar lección
|
|
This rough estimate is used during the initiating processes and in top-down estimates. The range of variance for the estimate can be from –25 percent to +75 percent.
|
|
|
Schedule performance index (SPI) empezar lección
|
|
Measures the project based on its schedule performance. The formula is SPI = EV/PV.
|
|
|
empezar lección
|
|
The difference between the earned value and the planned value. The formulas is SV = EV – PV.
|
|
|
empezar lección
|
|
Many vendors can provide what your project needs to purchase, but you prefer to work with a specific vendor.
|
|
|
empezar lección
|
|
Only one vendor can provide what your project needs to purchase. Examples include a specific consultant, specialized service, or unique type of material.
|
|
|
empezar lección
|
|
Monies that have already been invested in a project.
|
|
|
= (BAC – EV)/(BAC – AC). If you want to see if your project can meet the newly created estimate at completion, you’ll use this version of the formula: TCPI = (BAC empezar lección
|
|
= (BAC - EV) / (BAC - AC). If you want to see if your project can meet the newly created estimate at completion, you'll use this version of the formula: TCPI = (BAC
|
|
|
empezar lección
|
|
|
|
|
empezar lección
|
|
Costs that change based on the conditions applied in the project (the number of meeting participants, the supply of and demand for materials, and so on).
|
|
|
Variance at completion (VAC) empezar lección
|
|
A forecasting formula that predicts how much of a variance the project will likely have based on current conditions within the project. The formula is VAC = BAC – EAC.
|
|
|